The Brewery - Timeline (cont.)
Skip to a section:
Page 1 (6/05 - 5/06) |
Page 2 (6/06 - 8/06) |
Page 3 (9/06) |
Page 4 (10/06 - 12/06)
September 5, 2006
Poured concrete for trenches.
Poured the handicap ramp at the front entrance.
September 5, 2006 - Present
Worked on erecting the cold room.
September 8, 2006
Placed chillers on roof. The smaller one is for the cold room,
the larger one is for brewery glycol.
Removing the main chiller from its packaging and from the brewery.
Ed's Crane Service at work.
The two chillers in place.
September 11, 2006
Resurfaced front parking lot.
September 13, 2006
Pulled the two fermenters into standing positions.
September 18, 2006
Pulled the conditioning tank into a standing position.
September 20-21, 2006
Applied an epoxy coating to the floor around the trenches to
protect the concrete from harsh chemicals.
September 21, 2006
Clarifier arrived.
September 27-30, 2006
Attended GABF in Denver.
Click here for more pictures!