The Brewery - Timeline (cont.)


Skip to a section:
Page 1 (6/05 - 5/06) | Page 2 (6/06 - 8/06) | Page 3 (9/06) | Page 4 (10/06 - 12/06)


September 5, 2006
Poured concrete for trenches.
(Concrete truck) (Pouring concrete) (Pouring concrete) (Pouring concrete) (Pouring concrete) (Pouring concrete) (Pouring concrete) (Pouring concrete) (Pouring concrete)
Poured the handicap ramp at the front entrance.
(Pouring concrete for ramp) (Pouring concrete for ramp)

September 5, 2006 - Present
Worked on erecting the cold room.
(Walls) (Walls) (Walls)

September 8, 2006
Placed chillers on roof. The smaller one is for the cold room, the larger one is for brewery glycol.
Removing the main chiller from its packaging and from the brewery.
(Uncrating chiller) (Removing from brewery)
Ed's Crane Service at work.
(Crane) (Crane) (Hoisting chiller) (Hoisting chiller)
The two chillers in place.
(In place)

September 11, 2006
Resurfaced front parking lot. (Parking lot) (Parking lot)

September 13, 2006
Pulled the two fermenters into standing positions.
(Raising fermenter 1) (Raising fermenter 1) (Raising fermenter 1) (Raising fermenter 1) (Raising fermenter 2) (Raising fermenter 2) (Fermenters in place)

September 18, 2006
Pulled the conditioning tank into a standing position.
(Raising Brite Tank) (Raising Brite Tank)

September 20-21, 2006
Applied an epoxy coating to the floor around the trenches to protect the concrete from harsh chemicals.
(Epoxy) (Epoxy) (Epoxy) (Epoxy)

September 21, 2006
Clarifier arrived.
(Clarifier)

September 27-30, 2006
Attended GABF in Denver. Click here for more pictures!
(GABF Booth)

<-- Previous page | Next page -->


Copyright 2006 Skyscraper Brewing Company