The Brewery - Timeline (cont.)
Skip to a section:
Page 1 (6/05 - 5/06) |
Page 2 (6/06 - 8/06) |
Page 3 (9/06) |
Page 4 (10/06 - 12/06)
June 1, 2006
Cold room panels arrived.
June 7, 2006
Two fermenters and one conditioning tank shipped from factory in
China.
July 7, 2006
Fermenters and conditioning tank arrived.
July 12 - 31, 2006
Dug ditches for trench drains. Andrew helped do what he does best
- break things.
Here's how things looked after the concrete was cut.
July 14, 2006
Picked up keg washer. Juan Carlos and Diego helped unpack it.
August 24, 2006
Placed and anchored trenches.