The Brewery - Timeline (cont.)


Skip to a section:
Page 1 (6/05 - 5/06) | Page 2 (6/06 - 8/06) | Page 3 (9/06) | Page 4 (10/06 - 12/06)


June 1, 2006
Cold room panels arrived.
(Cold Room Panels) (Cold Room Panels)

June 7, 2006
Two fermenters and one conditioning tank shipped from factory in China.
(Tanks in factory) (Tanks in factory) (Loading tanks) (Loading tanks) (Loading tanks)

July 7, 2006
Fermenters and conditioning tank arrived.
(Unloading tanks) (Unloading tanks)

July 12 - 31, 2006
Dug ditches for trench drains. Andrew helped do what he does best - break things.
(Andrew breaking concrete) (Andrew breaking concrete) (Andrew breaking concrete)
Here's how things looked after the concrete was cut.
(Finished concrete cuts) (Finished concrete cuts) (Finished concrete cuts)

July 14, 2006
Picked up keg washer. Juan Carlos and Diego helped unpack it.
(Keg washer in truck) (Uncrating keg washer) (Keg washer)

August 24, 2006
Placed and anchored trenches.
(Anchoring trenches) (Anchoring trenches)